Grandstand Purlin and Roofing Replacement – Brisbane Grammar School

Touchstone Building Services (TBS) was engaged by Brisbane Grammar School to perform a complete roof and purlin replacement on the school’s Otto Nothling Hall grandstand structure. The project included the safe removal and replacement of damaged roofing components, reinforcement of structural steel members, and installation of compliant safety systems — all delivered within strict site access and operational timeframes.

773 Nudgee Road, Northgate QLD

Craig Derrick (Brisbane Grammar)

$291,637.90 (incl. GST)

Approximately 3 weeks

773 Nudgee Road, Northgate QLD

Craig Derrick (Brisbane Grammar)

$291,637.90 (incl. GST)

Approximately 3 weeks

    • TBS acted as Principal Contractor, coordinating trades, safety management, crane lifts, and traffic control.

    • All works completed under QBCC and WHS compliance with full documentation and certifications.

IMG_1464.jpg
IMG_1481.jpg
    • Installation of temporary fencing and exclusion zones.

    • Supply of mobile scaffolding towers and elevated working platforms (EWP, scissor and boom lifts).

    • Edge protection scaffolding (97 linear metres) with independent certification.

    • Comprehensive SWMS and induction process for all site personnel.

IMG_1340.jpg
IMG_1594.jpg
    • TBS acted as Principal Contractor, coordinating trades, safety management, crane lifts, and traffic control.

    • All works completed under QBCC and WHS compliance with full documentation and certifications.

IMG_1730.jpg
IMG_1833.jpg
    • Removal of existing Colorbond sheeting, flashings, insulation, and redundant safety wire.

    • Supply and installation of new .48 BMT Colorbond Spandeck roofing with 60mm anticon insulation.

    • Integration of drypan, barge, and throat flashings with UV-resistant Decktites.

    • Coordination of electrical isolation and reinstatement for lighting and PA systems mounted beneath the roof structure.

IMG_1706.jpg
IMG_1705.jpg
    • Demolition and reinstatement of internal plasterboard ceilings in Otto Nothling Hall.

    • Installation of 10mm ceiling-grade plasterboard, joint taping, sanding, and finishing.

    • Repainting of ceilings and wall touch-ups using Dulux Wash & Wear Low Sheen and Dulux Ceiling White systems.

IMG_1860.jpg
IMG_1861.jpg
    • Independent building certification and safety inspection.

    • Full photographic documentation and quality assurance report issued via OneDrive.

1_PHOTO-2025-10-20-07-47-41.jpg
IMG_1681.jpg
Here Section BG Image (5).png

Compliance & Quality Assurance

  • $20 million Public Liability Insurance

  • WHS and Environmental Management Plans

  • Building Certification and Q-Leave Levy compliance

Completed safely under live school conditions

Coordinated roofing and structural steel replacement across trades

Delivered with minimal disruption to school operations

“Touchstone Building Services delivered a complex grandstand roof and purlin replacement for Brisbane Grammar School, managing structural steelworks, roofing, insulation, and internal ceiling reinstatement under strict operational and safety requirements. The project highlights our capability to perform large-scale roofing and structural refurbishments in active environments while maintaining compliance, safety, and precision.”